Material Arrival Task List
Edit Order # Customer Job Description Task Due Date PO # Hours Left Material Arrival Pre-Shop Work Cut Sew Weld Fabric Seam Cut Down Shop Work SHA Frame Graphics Welded Frame Vendor Frame PC Drop Off PC Pick Up Take Down Install TD Install Help Install Help Proliner BNR Table CAD Shipping Install Follow-Up SH Task Employee Name Hours Worked Hours Remaining Update
Edit 01234
Kayla Guy
Thursday (5/7) 425 - 5/7 - 5/13 - - - - 5/19 - - - - - - - - - - - - - - - - -
Edit 279046
Salt Lake Brewing Co L.C.
job description for salt lake brewing co order Thursday (5/14) 25462 - 5/14 - Completed 1 5/20 - - - - 5/20 - - - - Completed 6/10 - - - Completed - - - Completed -
Edit 279046
Salt Lake Brewing Co L.C.
job description for salt lake brewing co order Thursday (5/14) 21592 - 5/14 - Completed 1 5/20 - - - - 5/20 - - - - Completed 6/10 - - - Completed - - - Completed -
Cut Task List
Edit Order # Customer Job Description Task Due Date Est. Hours Hours Left Material Arrival Pre-Shop Work Cut Sew Weld Fabric Seam Cut Down Shop Work SHA Frame Graphics Welded Frame Vendor Frame PC Drop Off PC Pick Up Take Down Install TD Install Help Install Help Proliner BNR Table CAD Shipping Install Follow-Up SH Task Employee Name Hours Worked Hours Remaining Update
Edit 01234
Kayla Guy
Wednesday (5/13) 2.00 2.00 5/7 - 5/13 - - - - 5/19 - - - - - - - - - - - - - - - - -
Edit SH0001
SH Task - Darin Coaching Meeting
darin coaching meeting Monday (7/6) 0.50 0.00 - - 7/6 - - - - - - - - - - - - - - - - - - - - - 7/6
Sew Task List
Edit Order # Customer Job Description Task Due Date Est. Hours Hours Left Material Arrival Pre-Shop Work Cut Sew Weld Fabric Seam Cut Down Shop Work SHA Frame Graphics Welded Frame Vendor Frame PC Drop Off PC Pick Up Take Down Install TD Install Help Install Help Proliner BNR Table CAD Shipping Install Follow-Up SH Task Employee Name Hours Worked Hours Remaining Update
Edit 279046
Salt Lake Brewing Co L.C.
job description for salt lake brewing co order Friday (5/22) 4.00 4.00 2 - Completed 5/22 5/20 - - - - 5/20 - - - - Completed 6/10 - - - Completed - - - Completed -
Weld Fabric Task List
Edit Order # Customer Job Description Task Due Date Est. Hours Hours Left Material Arrival Pre-Shop Work Cut Sew Weld Fabric Seam Cut Down Shop Work SHA Frame Graphics Welded Frame Vendor Frame PC Drop Off PC Pick Up Take Down Install TD Install Help Install Help Proliner BNR Table CAD Shipping Install Follow-Up SH Task Employee Name Hours Worked Hours Remaining Update
Edit 279046
Salt Lake Brewing Co L.C.
job description for salt lake brewing co order Wednesday (5/20) 2.00 2.00 2 - Completed 1 5/20 - - - - 5/20 - - - - Completed 6/10 - - - Completed - - - Completed -
Shop Work Task List
Edit Order # Customer Job Description Task Due Date Est. Hours Hours Left Material Arrival Pre-Shop Work Cut Sew Weld Fabric Seam Cut Down Shop Work SHA Frame Graphics Welded Frame Vendor Frame PC Drop Off PC Pick Up Take Down Install TD Install Help Install Help Proliner BNR Table CAD Shipping Install Follow-Up SH Task Employee Name Hours Worked Hours Remaining Update
Edit SH0002
SH Task - chad check compressor
Chad check compressor every friday Friday (4/24) 0.25 0.25 - - - - - - - 4/24 - - - - - - - - - - - - - - - - 4/24
Edit 01234
Kayla Guy
Tuesday (5/19) 2.00 2.00 5/7 - 5/13 - - - - 5/19 - - - - - - - - - - - - - - - - -
Edit 3
Kayla Guy
Thursday (6/11) 1.00 1.00 - - - - - - - 6/11 - - - - - - - - - - - - - - - - -
Edit SH0003
Unknown Customer
clean the horses Thursday (6/18) 0.75 - - - - - - - - 6/18 - - - - - - - - - - - - - - - - -
Edit 2
🔥
Kayla Guy (2/3)
Part 3: Awnings, Part 4: Awnings
(PROMOD) Alter (1) shade glide pamel Tuesday (6/23) 5.00 5.00 - - - - - - - 6/23 - - - - - - - - - - - - - - - - -
Graphics Task List
Edit Order # Customer Job Description Task Due Date Est. Hours Hours Left Material Arrival Pre-Shop Work Cut Sew Weld Fabric Seam Cut Down Shop Work SHA Frame Graphics Welded Frame Vendor Frame PC Drop Off PC Pick Up Take Down Install TD Install Help Install Help Proliner BNR Table CAD Shipping Install Follow-Up SH Task Employee Name Hours Worked Hours Remaining Update
Edit 279046
Salt Lake Brewing Co L.C.
job description for salt lake brewing co order Wednesday (5/20) 3.00 3.00 2 - Completed 1 5/20 - - - - 5/20 - - - - Completed 6/10 - - - Completed - - - Completed -
Vendor Frame Task List
Edit Order # Customer Job Description Task Due Date PO # Hours Left Material Arrival Pre-Shop Work Cut Sew Weld Fabric Seam Cut Down Shop Work SHA Frame Graphics Welded Frame Vendor Frame PC Drop Off PC Pick Up Take Down Install TD Install Help Install Help Proliner BNR Table CAD Shipping Install Follow-Up SH Task Employee Name Hours Worked Hours Remaining Update
Edit 279799
Michael Visser
Monday (5/11) 0.25 - - - - - - - - - - - - 5/11 - - - 5/11 - - - - - - - - -
Take Down Task List
Edit Order # Customer Job Description Task Due Date Est. Hours Hours Left Material Arrival Pre-Shop Work Cut Sew Weld Fabric Seam Cut Down Shop Work SHA Frame Graphics Welded Frame Vendor Frame PC Drop Off PC Pick Up Take Down Install TD Install Help Install Help Proliner BNR Table CAD Shipping Install Follow-Up SH Task Employee Name Hours Worked /
# of Employees
Hours Remaining Update
Edit 123789
Mike Peterson (1/3)
Part 2: Boat Covers, Part 3: Awnings
Tuesday (4/28) 2.00 0.00 - - Completed Completed - - Completed - - Completed - - - - 4/28 2 - - - - - - - - Completed
Install Task List
Edit Order # Customer Job Description Task Due Date Est. Hours Hours Left Material Arrival Pre-Shop Work Cut Sew Weld Fabric Seam Cut Down Shop Work SHA Frame Graphics Welded Frame Vendor Frame PC Drop Off PC Pick Up Take Down Install TD Install Help Install Help Proliner BNR Table CAD Shipping Install Follow-Up SH Task Employee Name Hours Worked /
# of Employees
Hours Remaining Update
Edit 123789
Mike Peterson (1/3)
Part 2: Boat Covers, Part 3: Awnings
Monday (5/11) 3.50 3.50 - - Completed Completed - - Completed - - Completed - - - - 4/28 5/11 - - - - - - - - Completed
Edit 279799
Michael Visser
Monday (5/11) 2.00 2.00 - - - - - - - - - - - 5/11 - - - 5/11 - - - - - - - - -
Edit 278862
Tulie Bakery
Awning - Put Up Put Up: (5) Shade Glide Panels Color: Pewter Stored: Here - Storage Containe... Thursday (5/14) 2.00 2.00 - - - - - - - - - - - - - - - 5/14 - - - - - - - - -
Edit 123789
Mike Peterson (1/3)
Part 2: Boat Covers, Part 3: Awnings
Saturday (5/16) 5.00 5.00 - - Completed Completed - - Completed - - Completed - - - - 4/28 5/16 - - - - - - - - Completed
Edit 279046
Salt Lake Brewing Co L.C.
job description for salt lake brewing co order Wednesday (6/10) 6.00 6.00 2 - Completed 1 5/20 - - - - 5/20 - - - - Completed 6/10 - - - Completed - - - Completed -
Proliner Task List
Edit Order # Customer Job Description Task Due Date Est. Hours Hours Left Material Arrival Pre-Shop Work Cut Sew Weld Fabric Seam Cut Down Shop Work SHA Frame Graphics Welded Frame Vendor Frame PC Drop Off PC Pick Up Take Down Install TD Install Help Install Help Proliner BNR Table CAD Shipping Install Follow-Up SH Task Employee Name Hours Worked Hours Remaining Update
Edit 278889
Primary Children's Hospital
big shade glide system Wednesday (5/6) 1.00 1.00 - - - - - - - Completed Completed - - - - - - Completed - - 5/6 - 5/8 5/8 - - -
Table Task List
Edit Order # Customer Job Description Task Due Date Est. Hours Hours Left Material Arrival Pre-Shop Work Cut Sew Weld Fabric Seam Cut Down Shop Work SHA Frame Graphics Welded Frame Vendor Frame PC Drop Off PC Pick Up Take Down Install TD Install Help Install Help Proliner BNR Table CAD Shipping Install Follow-Up SH Task Employee Name Hours Worked Hours Remaining Update
Edit 278889
Primary Children's Hospital
big shade glide system Friday (5/8) 1.00 1.00 - - - - - - - Completed Completed - - - - - - Completed - - 5/6 - 5/8 5/8 - - -
CAD Task List
Edit Order # Customer Job Description Task Due Date Est. Hours Hours Left Material Arrival Pre-Shop Work Cut Sew Weld Fabric Seam Cut Down Shop Work SHA Frame Graphics Welded Frame Vendor Frame PC Drop Off PC Pick Up Take Down Install TD Install Help Install Help Proliner BNR Table CAD Shipping Install Follow-Up SH Task Employee Name Hours Worked Hours Remaining Update
Edit 278889
Primary Children's Hospital
big shade glide system Friday (5/8) 2.00 2.00 - - - - - - - Completed Completed - - - - - - Completed - - 5/6 - 5/8 5/8 - - -
SH Task Task List
Edit Order # Customer Job Description Task Due Date Est. Hours Hours Left Material Arrival Pre-Shop Work Cut Sew Weld Fabric Seam Cut Down Shop Work SHA Frame Graphics Welded Frame Vendor Frame PC Drop Off PC Pick Up Take Down Install TD Install Help Install Help Proliner BNR Table CAD Shipping Install Follow-Up SH Task Employee Name Hours Worked Hours Remaining Update
Edit SH0002
SH Task - chad check compressor
Chad check compressor every friday Friday (4/24) - - - - - - - - - 4/24 - - - - - - - - - - - - - - - - 4/24
Edit SH0001
SH Task - Darin Coaching Meeting
darin coaching meeting Monday (7/6) - - - - 7/6 - - - - - - - - - - - - - - - - - - - - - 7/6